Expected Construction Activities: 6/3/17 & 6/10/17
On Saturday, June 3 and June 10, Dalton will do exterior work on Dalton's roof top from 9:00 AM - 6:00 PM pending good weather conditions.
Please be advised that Saturday work will take place for the next two weekends as permitted by the Department of Buildings (DOB). Dates and times are subject to change as weather conditions and unforeseen circumstances may influence the progress of work.
The exterior work on the roof will consist of:
Electrical relocation
Selective abatement (reduction or lessening) and demolition at stair and elevator bulkheads
Roof protection
The School expects minimal impact to building access, vehicular traffic, and pedestrian walkways.