Expected Construction Activities: 12/23/17 - 1/6/18
The following summarizes expected construction over the school break, which includes relevant work in front of the 89th Street building. Saturday work is planned for 12/23, 12/30, and 1/6.
Our construction team will complete assembly of additional scaffolding and hoist machinery in front of the school. In addition, the pavement will be restored upon completion of the upgraded water system.
We will coordinate building access and deliveries throughout the process. The building will be closed and we anticipate minimal impact to vehicular traffic and pedestrian walkways.
Saturday work As outlined above, exterior work is planned for December 23, 30, and January 6 from 9:00 AM - 6:00 PM pending DOB approval.
Weekday construction hours Construction work will occur during normal DOB construction hours on weekdays from 7:00 AM - 6:00 PM with no exterior work beginning prior to 8:00 AM. No project deliveries will be permitted before 7:30 AM. All dates and times are subject to change as weather conditions and unforeseen circumstances may impact the progress of work.