The following is a summary of expected construction activities for August including relevant information about the exterior, interior, projected crane work, and DOB permitted construction hours.
Exterior work:
Front
Three full days of street closure for crane work (see more details below)
Rooftop
Rooftop protective netting maintenance
Selective removal of mechanical equipment and masonry
Ongoing electrical relocation and steel/deck work
Concrete deck installation on 14th floor and new roof
Interior work:
Existing column reinforcement and enclosure
New riser work
Drywall and millwork installation
Interior painting
Street closure for crane work:
As a reminder, 89th Street (between Lexington and Park Avenue) will be closed from Tuesday, August 8 through Thursday, August 10. Crane work will occur during extended hours as permitted by the DOB between 7:00 AM - 8:00 PM. Our construction team will coordinate building access and deliveries throughout the process. During the full street closure, Dalton will aasign a minimum of six flag persons and security on the street 24-hours a day to facilitate emergency vehicular access and safe pedestrian passage. Construction Hours (excluding crane work):
Construction work will occur during normal DOB construction hours on weekdays from 7:00 AM - 6:00 PM with no exterior work beginning prior to 8:00 AM. No project deliveries will be permitted before 7:30 AM on weekdays.
Saturday work:
Please be aware that Saturday work will take place on August 5, 12, 19, 26 and September 2 from 9:00 AM - 6:00 PM, pending DOB approval. The construction work includes interior work and necessary rooftop modifications. We anticipate minimal impact to building access, vehicular traffic, and pedestrian walkways.
All dates and times are subject to change as weather conditions and unforeseen circumstances may impact the progress of work.